Published 5 November 2026. Sources last checked 5 November 2026.
Some extensions can be built without applying for planning permission, under rules called permitted development. Others need a full householder application. The answer depends on the size and position of the extension, what has been done to the house before and where it is.
This is a summary of the limits on the Planning Portal for houses in England. The Portal itself calls its guidance an introduction, and says to check with your local planning authority before starting work.
The main permitted development limits
Single-storey rear extensions
- Up to 4 metres beyond the original rear wall for a detached house
- Up to 3 metres for any other house
- No more than 4 metres high
Extensions of more than one storey
- No more than 3 metres beyond the rear wall
Side extensions
- Single storey only
- Up to 4 metres high
- No wider than half the width of the original house
General limits
- Extensions and other buildings can cover no more than half the land around the original house
- No higher than the highest part of the existing roof
- Eaves no higher than the existing eaves
- Eaves no higher than 3 metres if the extension is within 2 metres of a boundary
- Exterior materials must be similar in appearance to the existing house
What “original house” means
These limits are measured from the original house, not the house as it stands today. If an earlier owner has already extended it, part of your allowance may have been used up. This catches many people out, so check the planning history first.
Larger rear extensions and prior approval
Outside designated land and Sites of Special Scientific Interest, you can ask for a larger single-storey rear extension through the prior approval process. It raises the limit to 8 metres for a detached house and 6 metres for any other house.
Prior approval is a shorter process than a full application, but you still need to apply and wait for a decision before you start. Neighbours can raise objections as part of it.
When the rules are tighter
Permitted development rights can be reduced or removed altogether.
Designated land includes conservation areas and national landscapes, among others. There, cladding the outside is not permitted, side extensions need permission and rear extensions of more than one storey need permission.
Article 4 directions are made by local planning authorities. They remove some or all permitted development rights in a given area, and they are often used in conservation areas.
Planning conditions on the original permission for your house may also have removed these rights. This is common on newer estates, so check the original permission.
Flats and maisonettes do not have these rights in the same way, and listed buildings need their own consents.
Prove it: lawful development certificates
If you think your extension is permitted development, you can apply for a lawful development certificate. GOV.UK explains that a certificate confirms a proposed use or development would be lawful for planning purposes. It is not compulsory, but it gives you written evidence, which is useful when you come to sell.
If you need planning permission
Many well-designed extensions need an application, and that should not put you off. A householder application lets your architect design what the house really needs, rather than fitting within fixed limits. Consider asking your local planning authority for pre-application advice if the design is unusual or the site is sensitive.
Planning is only one approval
Permitted development only deals with planning. You will separately need:
- Building regulations approval, for the structure, fire safety, insulation, drainage and more
- Party wall notices, if you are working on a shared wall or digging near a neighbour’s foundations
- A build over agreement with your sewerage company, in some cases. In its area, Thames Water says you are likely to need one if building within 3 metres of a public sewer
What to do next
- Check the planning history of the house, including any past extensions.
- Ask whether the house is on designated land, or subject to an Article 4 direction.
- Sketch what you want before looking at the limits, so the rules do not design the house for you.
- Ask your architect to test it against the rules.
Some extensions can be built without planning permission and others need it. Your architect, or our in-house architect, usually applies. See our extensions page, or our rear extension and garden room in Wimbledon.
Sources
- Planning Portal: Extensions and planning permission
- GOV.UK: Lawful development certificates
- GOV.UK: When is planning permission required?
- Thames Water: Do I need a build over agreement?
This guide is general information for homes in England, not legal, tax or planning advice. Rules change and every house differs, so check with your local planning authority, your building control body or a qualified adviser before relying on it.