How a complete house refurbishment runs, stage by stage

The usual order of a complete house refurbishment, from survey and approvals to strip-out, services, finishes and handover, with what to decide at each stage.

A refurbished bathroom with marble-effect tiles, a bath, a black-framed shower and a wood-effect vanity unit

Published 5 November 2026. Sources last checked 5 November 2026.

A complete refurbishment takes a house back to its structure and rebuilds the inside. The work looks chaotic from the street, but it follows a firm order. Each trade depends on the one before it, so most problems on these projects start with a decision made late or a stage rushed.

Here is the usual sequence. Every house differs, but the logic holds.

1. Survey and brief

Start with what the house is and what you want from it. A measured survey gives accurate drawings. A structural survey shows what the frame, floors and roof can do. Write down how you want to live in the house, room by room, before anyone draws a solution.

Ask about asbestos early. The Health and Safety Executive says asbestos may be part of any commercial or domestic building built or refurbished before the year 2000. If your house falls into that group, it should be checked before work disturbs the fabric of the building.

2. Design and approvals

The design sets the layout, the structure and the services. This is also when you find out which approvals the work needs:

  • Planning permission, or confirmation that the work is permitted development
  • Building regulations approval for structural work, new heating and many other changes
  • Party wall notices if the work affects a shared wall or digs close to a neighbour’s foundations

These run on their own timescales, and they should be built into the programme from the start. See our guides to building regulations and the Party Wall Act.

3. Specification, price and programme

A builder can only price what has been described. The more complete the drawings and specification, the more reliable the price. Kitchens, bathrooms, joinery, flooring and lighting all need a clear description or a stated allowance.

We set out an itemised quotation, a payment plan and a contract before any work starts. Whoever you appoint, ask for the same things in writing. Our guide to comparing quotes explains what to look for.

4. Strip-out

The old finishes, kitchens, bathrooms and redundant services come out. This is when the house reveals itself. Old alterations, hidden damp and surprises in the structure often appear at this stage, which is why it pays to hold a contingency and to expect some design decisions to be revisited.

Our bungalow renovation in Beddington shows a house at this point, stripped back to its structure with new timber framing going in.

5. Structure

New steels, openings, floors and roof work go in next. Building control inspects at the stages it has agreed. Anything that affects a party wall follows the award or agreement in place.

Getting the structure level and true matters more than it seems. Stone, large-format tile and fitted joinery all show up an uneven wall or floor.

6. First fix

Electricians, plumbers and heating engineers run cables and pipes through the open structure, before walls and ceilings close up. This is the last easy moment to change a socket position, a lighting circuit or a radiator. Walk the house with your drawings before it is covered.

7. Insulation, plastering and drying

Insulation, boarding, screeds and plaster go on. Wet trades need time to dry. Rushing this stage is a common cause of later trouble, because timber floors and joinery move when they are fitted into damp rooms.

8. Second fix and finishes

Now the house starts to look like a home. Joinery, doors, kitchens, bathrooms, tiling, decoration and flooring go in, usually with the most delicate finishes last and with protection over anything already complete. Sockets, switches, lights and sanitaryware are fitted.

9. Snagging and handover

Walk the finished house with the builder and list anything that needs attention. Then collect the paperwork: certificates, manuals and warranties. Keep them. GOV.UK notes that you need certificates of compliance to sell your home.

Who is responsible for safety

Most homeowners are “domestic clients” under the Construction (Design and Management) Regulations 2015. HSE explains that client duties normally pass to the contractor or, on a project with more than one contractor, to the principal contractor. You can ask a designer to take them on instead, with a written agreement.

Where to go from here

Our complete refurbishments page shows the work we do, and our approach sets out how a project runs with us. If you are also deciding whether to keep the house at all, read refurbish or rebuild.

Sources

This guide is general information for homes in England, not legal, tax or planning advice. Rules change and every house differs, so check with your local planning authority, your building control body or a qualified adviser before relying on it.